UAE delays launch of first nuclear reactor until 2018

Egypt Today, egypt today

Egypt Today, egypt today UAE delays launch of first nuclear reactor until 2018

the Barakah nuclear plant will deliver up to a quarter of the UAE’s electricity
Abu Dhabi - Arab Today

The UAE on Friday was forced to delay by a year the start-up of its first nuclear reactor as the company established to run it has not yet received an operating license.
The world’s largest single nuclear project, the Barakah nuclear plant will deliver up to a quarter of the UAE’s electricity when completed around 2020 and is led by Korea Electric Power Corporation (KEPCO), which is building four APR-1400 reactors simultaneously.
Confirming a Reuters report on Thursday, Emirates Nuclear Energy Corporation (ENEC) said that work on the first reactor had been completed but Nawah, the ENEC-KEPCO joint venture set to run the plant, had not yet received an operating license from the UAE’s Federal Authority for Nuclear Regulation (FANR).
ENEC announced “an extension for the start-up of nuclear operations for Unit 1, from 2017 to 2018, to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as a reinforcement of operational proficiency for plant personnel.”
“FANR is conducting a...review of the operating license application...and numerous inspections of construction and operational readiness,” ENEC said.
Experts from the International Atomic Energy Agency (IAEA) and the World Association of Nuclear Operators (WANO) will also assess Barakah’s infrastructure and personnel.
“These assessments will take place before we anticipate being granted our operating license and begin the process of loading fuel,” said Nawah’s acting CEO Mohammed Sahoo Al-Suwaidi.
“We recognize the scale of both our responsibilities and of the challenges that lie ahead of us,” he said.
The UAE is building a nuclear industry from scratch, hiring nuclear physicists, setting up a regulator, training operators and setting up institutes for radiation monitoring and accident prevention.
India, Brazil, South Africa, Iran, Pakistan and Turkey have done this or are also in the process of developing their nuclear industries.
South Korea’s KEPCO — a newcomer in the business of building nuclear plants abroad — has built the UAE plants on time and on budget, in contrast with years of delay and billions in cost overruns at projects of leading Western builders Areva and Westinghouse.

Source: Arab News

egypttoday
egypttoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

uae delays launch of first nuclear reactor until 2018 uae delays launch of first nuclear reactor until 2018



GMT 13:15 2017 Thursday ,26 January

Wild pandas frequently spotted in China

GMT 07:18 2018 Friday ,05 October

Jordan receives $1 billion from Gulf aid package

GMT 12:01 2018 Tuesday ,09 January

Bacteria makes blue jeans green

GMT 11:54 2017 Saturday ,14 October

OPEC expects higher demand for its oil

GMT 09:36 2018 Thursday ,01 November

Trump says US-Mexico border troops could hit 15,000

GMT 08:15 2018 Wednesday ,12 September

Us-China Trade Spat Looms Over Regional Wef Meeting

GMT 09:58 2018 Friday ,07 September

Osaka makes history in reaching US Open final

GMT 00:42 2012 Tuesday ,16 October

The Saudi nuclear program

GMT 10:43 2016 Thursday ,17 November

Lionel Messi Voted Best Player of Last 10 Years

GMT 12:33 2017 Tuesday ,03 October

GCC and France discuss cooperation

GMT 08:54 2017 Thursday ,27 July

Russia regrets UNSC refusal to condemn attack

GMT 00:38 2017 Monday ,08 May

Israeli forces push deep into Gaza

GMT 11:54 2017 Thursday ,07 September

Gulf Air increases Moscow daily flights

GMT 17:16 2017 Sunday ,19 November

Delhi half-marathon to go ahead

GMT 13:27 2017 Thursday ,23 November

Football: FIFA defendants 'blinded by greed,'

GMT 06:12 2017 Monday ,18 December

Uber denied new license in northern
 
 Egypt Today Facebook,egypt today facebook  Egypt Today Twitter,egypt today twitter Egypt Today Rss,egypt today rss  Egypt Today Youtube,egypt today youtube  Egypt Today Youtube,egypt today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

egypttoday egypttoday egypttoday egypttoday
egypttoday egypttoday egypttoday
egypttoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
egypttoday, Egypttoday, Egypttoday